Parks in Progress

The "New" Newport Park
SiteMap
County Commissioners approved funding for and gave Parks & Recreation permission to apply to the Parks and Recreation Trust Fund for a grant to build a community park next to the Newport Middle School, on 11 acres that were donated by the Board of Education in exchange for improvements to the middle school ball fields. The County was awarded $500,000 in grant funds and began construction in the Fall of 2008 with grading, utilities installation and seeding. The County Health Department contributed fitness stations on the walking trail that were funded by a $20,000 Eat Smart Move More Community Grant. Site Map
Construction Schedule The County anticipates construction of park amenities as scheduled below.
Amenity
Construction Start-Stop
Notes
Recreation Center
Jan 2010-Jul 2010
Maintenance Building
Jan 2010-Mar 2010
Ballfield Lighting
Jan 2010-Apr 2010
Ballfields, located on school property, will be available for play Fall 2010
Tennis Courts
Feb 2010-Jun 2010
Small Structures
Mar 2010-Jun 2010
Picnic shelter, gazebo, bandshell
Pave Parking Lot
May 2010-Jun 2010
Landscaping
Apr 2010-Jun 2010

Requests for Bids for the work above will be posted at www.carteretcountygov.org/rfprfq.asp.